Construction at Fairbanks Field by Legacy Place Department : Parks and Recreation Type : Announcements Construction of the new parking lot at Fairbanks field has begun. below is the tentative schedule going forward. 1) 02/23/09 to 02/27/09 Cut trees and clear lot. COMPLETED 2) 03/02/09 to 03/20/09 Cut hill and haul excess fill. COMPLETED 3) 03/23/09 to 03/31/09 Remove old asphalt and subgrade lot. COMPLETED 4) 04/01/09 to 04/10/09 Relocate fence. COMPLETED 5) 04/13/09 to 04/31/09 Install drainage system. COMPLETED 6) 05/04/09 to 05/08/09 Gravel parking lot and sidewalks ready for paving. COMPLETED 7) 05/11/09 to 05/15/09 Binder coat of asphalt. ( by DPW) COMPLETED 8) 05/18/09 to 05/26/09 Install curbing. ( by DPW ) COMPLETED 9) 05/27/09 to 06/05/09 Landscaping. 10) 06/08/09 to 06/15/09 Finish paving. ( by DPW ) |