Rustcraft Rd Sewer Improvements Project - Work Schedule for week of 8/3

Post Date: 07/31/2020 9:00 AM

To date, RJV has installed approximately 2,500 LF (approx 51% of the total 4,885 LF to be installed) of the 10" Ductile Iron Force Main. 

For the week of August 3rd, RJV Construction Corp. (Contractor) will performing the following activities:

  • Excavation for and installation of the 10" force main continuing near Station 25+00 to Station 17+00.

Police details will be present to direct traffic around the work area.

For up-to-date information and photos regarding this project, please be sure to subscribe to Engineering Project Updates by clicking here.

You can download a copy of a map showing the project limits and/or construction plans at the Engineering Department's Rustcraft Road Sewer Improvements Project page by clicking here.