The Town's contractor, Lorusso Corp., will mill and repave Lower East Street from Washington Street to the Boston city line. Please review the schedule and important information below.
Project Schedule:
- Thursday, October 23 – Friday, October 24: Road milling (removal of 2" of existing asphalt)
- Monday, October 27 – Tuesday, October 28: Structure and utility box adjustments, patching
- Wednesday, October 29 – Thursday, October 30: Paving
What You Need to Know:
- Parking Restrictions
- No parking on Lower East Street beginning at 7:00 AM Thursday, October 23
- Remove all vehicles from the roadway before work begins
- Trash & Recycling Collection
- Place carts curbside by 7:00 AM on your regular collection day
- Boston Carting will collect on your normal schedule
- Traffic & Access
- Police details will be present during milling operations
- Expect minor delays throughout the project
- Vehicle access will be temporarily restricted at certain times
Please Note: This schedule is weather-dependent and subject to change without notice.
The Department of Public Works appreciates your cooperation and patience during this project. For questions or concerns, please contact:
Joe Flanagan, Director of Public Works
Phone: 781-751-9350
Email: Jflanagan@dedhamma.gov