Town of Dedham
Home MenuBussey Street Bridge (MassDOT)
Roadway and Sidewalk Improvements on Bussey Street including Bridge Construction (MassDOT Project #607899)
Please use the following links to access Project Updates from the MassDOT Project Team since construction began:
- November 27, 2024
- October 18, 2024
- July 11, 2024
- April 5, 2024
- October 16, 2023
- September 15, 2023
- September 8, 2023
About the Project
The Massachusetts Department of Transportation has prioritized the replacement of the Bussey Street Bridge in Dedham as a result of the following observations that the newly constructed bridge will address:
| ISSUE | IMPROVEMENT |
|---|---|
| Deficient pedestrian accommodations |
|
| No designated bicycle facilities |
|
| Intersection safety & capacity Issues |
|
| Deficient Drainage and Pavement Conditions |
|
| Deficient Bridge |
|
Project Contact Information
Questions or comments about the project can be submitted to the following MassDOT Representative:
Dan Fielding, Legislative Liaison
Massachusetts Department of Transportation
Mailing Address: 10 Park Plaza Suite 4160, Boston, MA 02116
Office Phone: 857-368-8959
Email: Daniel.fielding@dot.state.ma.us
Bridge Closure and Detours
The Bussey Street Bridge over Mother Brook will be closed starting September 18, 2023, and remain closed until Spring of 2025. The bridge will be replaced during this time. The temporary detour plan is outlined below and pedestrian access will be maintained over the existing bridge during construction. Access to all properties along Bussey Street, INCLUDING CONDON PARK, will be maintained during construction while the bridge is closed.
Temporary Detour Plan:
- High Street to Maverick Street to Colburn Street to Bussey Street
- Sawmill Lane to Dedham Boulevard to Harding Terrace to Colburn Street to Bussey Street
Reminder: Access to all properties along Bussey Street, INCLUDING CONDON PARK, will be maintained during construction while the bridge is closed.
Construction Schedule
- Mid-Late September 2023 - (Detours beginning September 18, 2023)
- Bridge closure and detour
- Pedestrian Management Implementation
- Fall 2023 through Spring 2024
- Phase 1 Bridge Demolition and Construction
- Summer 2024 through Fall 2025
- Phase 2 Bridge Demolition and Construction
- Fall 2023, Spring 2024 through Fall 2024
- Drainage work along Bussey Street
- Summer 2024 through Fall 2024
- Sidewalk, water, and lighting at Bussey Street Intersection
- Spring 2025 through Summer 2025
- Micro-milling, Full-depth road box widening, and final paving
- Summer 2025
- Bridge opening
Work Hours
Typical Work Shift:
- Monday through Friday
- 7:00 AM to 3:30 PM each day
- One Lane Alternating Traffic between 9:00 AM and 3:00 PM
No work shall be done on this contract on Saturdays, Sundays, or Holidays or not be allowed the day before or the day after a long weekend which involves a Holiday without prior approval by the Engineer. Contractor may request through MassDOT to work occasional overnight work in order to minimize traffic obstruction during roadway paving operations.
Public Meeting Materials and Information
- MassDOT hosted two Public Informational Hearings, one remote and one in-person, on Wednesday, August 16, 2023. Copies of the meeting flyer and presentation are listed below:
- MassDOT hosted a Design Public Hearing (prerecorded) on December 9, 2020 at the 25% design milestone. Copies of past meeting materials and information, including the recording, are listed below:
